When a Task with one of the Statuses listed below has gone past it's Due Date, the Task Status will automatically change to Delayed.
The automation can be turned off by an Admin under Settings> Workspace and User Settings > Tasks. When toggled on, this will disable the automation across the entire Workspace (all Processes).
Below are the statuses that will change to 'Delayed' when automation is enabled:
- Not Started
- In Progress
- Ready for Review
- At Risk
- Further Action Required
- Other
Conversely, the following statuses will NOT be moved to Delayed when the automation is enabled:
- Completed
- Postponed
- Guidance
- Ignored
- N/A